Linsheng , Emergency Lighting Testing And Maintenance

 

      You must ensure regular inspections and regular maintenance and maintenance, regardless of the size of the house and any defects as quickly as possible.

  You or some of the qualified personnel you specify can perform certain inspections and routine maintenance work. A person with the ability is a person who has the necessary training or experience to obtain the necessary tools, equipment and information, and who can perform the identified tasks.

  Maintenance may need to be performed by a qualified service engineer.

  In the case of contractors, third-party certification is a method that can reasonably guarantee the quality and ability of work.

  linsheng     recommends checking and testing as follows.

  Daily inspection

  All safety lighting fixtures have a visual indicator, usually a small red light that will be illuminated when working properly. This indicates that the unit cell is receiving a constant charge from the main power source. This indicator should be checked daily for validity. This simple inspection can be carried out by staff who work in a particular area in units in the area.

  Any defects should be reported immediately for remediation.

  Monthly inspection

  The test device is operated in emergency mode by operating the device. If an integrated test device is not provided, the sub-circuit (not the main power supply) for that particular area should be interrupted for a period of time to check for the presence of all units, clean and functioning properly.

  At the end of the test, power should be restored and a final check of each unit should be performed to ensure proper operation of the main power indicator.

  The date and results of the test should be recorded and any defects reported for immediate remediation.

  Six months inspection

  Each unit should be tested on a monthly basis, but the 3-hour unit is 1 hour and the 1-hour unit is 15 minutes.

  The date and results of the test should be recorded and any defects reported for immediate remediation.

  Annual inspection

  The full rated duration of the emergency light (eg 3 hours) must be tested. At the end of this test, the emergency light must still work.

  The results must be recorded and these results must be corrected as soon as possible if a failure is detected.

  Each unit should be tested on a monthly basis, but the period should be tested based on the full battery duration of the equipment. This may be 1 to 3 hours.

  

https://www.linsheng.com